Fanita Drive Resurfacing
Published Friday, August 8, 2025
Concrete pedestrian ramps will be installed on Fanita Dr from Mission Gorge Rd to Prospect Ave from August 18-25.
Asphalt berm repairs are scheduled between September 2-5.
Asphalt patching is scheduled on October 8-10.
The final steps of resurfacing are scheduled between October 10-20.
Visit our Street Maintenance webpage to see a visual timeline of cape sealing in a new window.
Please check back for schedule updates or contact the Engineering Dept. at (619) 258-4100 x 167.